1. A contract provides that if the buyer defaults, the seller 'shall retain the earnest money as liquidated damages as the seller's sole and exclusive remedy.' The buyer defaults, and the seller's actual loss is far greater than the deposit. What may the seller recover?
Answer & explanation
Answer: C. An enforceable liquidated damages clause that is the exclusive remedy limits the seller to the agreed amount, even if actual losses are larger. It is enforceable when it was a reasonable forecast at signing and not a penalty. Recovering the deposit plus actual damages would contradict the 'sole and exclusive remedy' language.